How do you calculate quantities of steel?
How do you calculate quantities of steel?
Calculate Steel quantity in slab as 1% of volume of concrete = 0.01× 7850× 3= 236kg:- according to using Thumb Rule Steel quantity required for RCC slab should be 1% of total volume of concrete, here steel density = 7850 kg/m3, so quantity of steel in slab = 0.01× 7850× 3= 236kg.
How many kg of steel is required in 1m3 of concrete?
78.50 kg
Minimum quantity of steel required for 1 m3 concrete beam is 1%, now 1% of 1m3 = 0.01 m3, and we know that 1m3 steel weight is 7850 Kg, so weight of 0.01 m3 steel = 0.01 × 7850 = 78.50 kg, so minimum quantity of steel required for 1m3 concrete beam is 78.50 Kg.
How do you calculate steel per square meter?
Thumb rule for Steel required for RCC slab is 80 kgs/m3, then quantity of steel required for 100 sq ft ( 1.18 m3) rcc slab is equal to = 80 × 1.18 = 94.5 Kgs.
How do I calculate steel in Excel?
Steps to Calculate Steel Quantity
- Enter Length and Width of your slab in ft in Excel Sheet. ( Convert Inches to feet)
- Enter the Thickness of the slab in mm only.
- Enter Main and distribution steel diameter in Excel Sheet.
- Enter Cover Details. (
- Enter Spacing of Main bent bar and Distribution steel bars in mm only.
What is the formula for weight of steel?
Steel weight formula = πD*2/ 4 × L × density, where w = weight of steel, π = 3.14, D = diameter of Steel bar in mm, L= length of Steel bar =1m and density = 7850 kg/ m3.
What does 1m3 of steel weigh?
7850
A guide to the weight of common engineering metals, expressed as kgs per cubic metre
Metal or Alloy | Kg /Cu. Mtr |
---|---|
Steel | 7850 |
Titanium | 4500 |
Tungsten | 19600 |
Zinc | 7135 |
What is unit of steel?
Unit weight of steel is 7850 kg/m³.
How do you calculate cubic meters of steel?
Thumb rule for steel in slab = 1% to 1.5% Minimum quantity of steel required for 1m3 concrete slab is 1%, now 1% of 1m3 = 0.01 m3, and we know that 1m3 steel weight is 7850 Kg, so weight of 0.01m3 steel = 0.01 × 7850 = 78.50 kg, so minimum quantity of steel required for 1m3 concrete slab is 78.50 Kg.
How do you calculate quantity of material?
The quantities of materials for 1 m3 of concrete production can be calculated as follows: The weight of cement required = 7.29 x 50 = 364.5 kg. Weight of fine aggregate (sand) = 1.5 x 364.5 = 546.75 kg. Weight of coarse aggregate = 3 x 364.5 = 1093.5 kg.
How do you calculate material quantity in construction?
Approximate cost on various work of material to complete the construction for 1000 ft 2
- Total Cost. = Builtup area × Approx cost per sq. ft. = 1000 × 1000. = 1000000.00 Rs.
- Amount of Aggregate Required. = Builtup area × 0.608. = 1000 × 0.608. = 608.00 Ton.
- Flooring. = Builtup area × 1.3. = 1000 × 1.3. = 1300.00 Sq.